How Long Does FedRAMP Authorization Really Take in 2024?
Q: How long does FedRAMP authorization actually take?
TL;DR: While FedRAMP PMO says 6-12 months, most organizations take 12-24 months for first authorization. Traditional approach: 13-22 months. With automation: 14-22 weeks (3.5-5.5 months). Documentation quality, evidence collection, and remediation are the main time drivers.
The Official Timeline vs. Reality
The FedRAMP PMO says the process takes "6-12 months." In practice, most organizations take 12-24 months for their first authorization.
Traditional FedRAMP Timeline Breakdown
Phase 1: Preparation (3-6 months)
- Readiness Assessment: 2-4 weeks
- Gap Remediation: 2-5 months
- 3PAO Selection: 1-2 months
- Kickoff: 2-4 weeks
Phase 2: Documentation (6-9 months)
- SSP Development: 4-6 months
- Policy Documentation: 2-3 months
- Evidence Collection: Ongoing, 2-3 months
- Review Cycles: 1-2 months
Phase 3: Assessment (2-3 months)
- SAP Development: 2-3 weeks
- Assessment Testing: 2-4 weeks
- SAR Development: 3-4 weeks
- Package Review: 2-3 weeks
Phase 4: Authorization (2-4 months)
- Initial Package Review: 4-6 weeks
- Remediation: 4-8 weeks
- Final Review: 2-4 weeks
- ATO Issuance: 1-2 weeks
Total Traditional Timeline: 13-22 months
What Slows Organizations Down?
1. Documentation Quality (60% of delays)
- Incomplete control descriptions
- Missing evidence references
- Vague implementation statements
- Inconsistencies between documents
2. Evidence Collection (25% of delays)
- Manual screenshot collection
- Difficulty organizing evidence
- Evidence becomes outdated
- Missing evidence for controls
3. Remediation (15% of delays)
- Finding discovered late
- Technical debt payoff
- Policy gaps
- Control implementation weaknesses
Accelerated Timeline with Automation
Using FedRampGPT
Phase 1: Setup (1-2 weeks)
- Connect data sources: 1-2 days
- Initial scan: 1 hour
- Review AI mappings: 3-5 days
- Gap analysis: Instant
Phase 2: Documentation (3-6 weeks)
- Auto-generate SSP Appendix A: 1 day
- Review and customize: 2-3 weeks
- Policy templates: 1 week
- Continuous evidence collection: Automated
Phase 3: Assessment (6-8 weeks)
- 3PAO coordination: 2 weeks
- Assessment: 2-3 weeks
- SAR generation: 2-3 weeks
Phase 4: Authorization (4-6 weeks)
- Package submission: 1 week
- Review and remediation: 2-3 weeks
- Final approval: 1-2 weeks
Total Automated Timeline: 14-22 weeks (3.5-5.5 months)
Agency vs. JAB Path
Agency Authorization
- Timeline: Typically faster (6-12 months)
- Benefit: Work with specific agency
- Limitation: Must reuse evidence for other agencies
JAB Authorization (P-ATO)
- Timeline: Longer (12-24 months)
- Benefit: Accepted by all agencies
- Process: More rigorous review
Factors That Impact Your Timeline
You Can Control:
- ✅ Quality of initial documentation
- ✅ Completeness of evidence
- ✅ Response time to 3PAO questions
- ✅ Resources dedicated to FedRAMP
- ✅ Use of automation tools
You Cannot Control:
- ❌ JAB review queue length
- ❌ 3PAO availability
- ❌ FedRAMP PMO response times
- ❌ Government holidays and shutdowns
Timeline Comparison: Case Studies
Case Study 1: Traditional Manual Approach
- Company: SaaS startup, 50 employees
- Baseline: Moderate
- Approach: Manual documentation, consultant support
- Timeline: 18 months
- Cost: $450K
- FTE: 2.5 full-time
Case Study 2: Automated with FedRampGPT
- Company: SaaS startup, 40 employees
- Baseline: Moderate
- Approach: FedRampGPT automation + 3PAO
- Timeline: 4.5 months
- Cost: $180K
- FTE: 0.5 full-time
How to Accelerate Your Timeline
1. Start with SOC 2
If you have SOC 2, you've already:
- Built compliance processes
- Documented security controls
- Collected evidence
- Worked with auditors
This can cut 3-6 months off your FedRAMP timeline.
2. Automate Evidence Collection
Manual evidence collection consumes 40% of your time. Automation reduces this to near-zero:
- AWS APIs → CloudTrail, Config, IAM data
- GitHub → Change management evidence
- Okta → Access control evidence
- Splunk → Audit log evidence
3. Use AI for Documentation
Writing 325 control descriptions manually takes 6-9 months. AI can generate draft descriptions in days based on your actual infrastructure.
4. Engage 3PAO Early
Don't wait until documentation is "perfect." Engage your 3PAO during development for continuous feedback.
5. Parallel Work Streams
Work on multiple aspects simultaneously:
- Team A: SSP sections 1-10
- Team B: Appendix A controls
- Team C: Supporting appendices
- Team D: Evidence collection
Month-by-Month Traditional Timeline
| Month | Activities | Deliverables |
|---|---|---|
| 1-2 | Readiness assessment, gap analysis | Gap report, remediation plan |
| 3-5 | Remediate gaps, select 3PAO | Improved security posture, 3PAO contract |
| 6-9 | SSP development | Complete SSP package |
| 10-12 | 3PAO assessment | SAR (Security Assessment Report) |
| 13-15 | Remediation of findings | Updated SSP and POA&M |
| 16-18 | Final review and ATO | Authority to Operate (ATO) |
Red Flags That Add Time
- 🚩 No security team in place (+3-6 months)
- 🚩 No existing compliance experience (+6 months)
- 🚩 Complex multi-tenant architecture (+3 months)
- 🚩 Legacy systems or technical debt (+4-6 months)
- 🚩 No Infrastructure as Code (+2 months)
- 🚩 Decentralized infrastructure (+3 months)
The Bottom Line
Traditional Approach: 12-24 months, $250K-$500K
With FedRampGPT: 3-6 months, 60-70% cost reduction
Get Your Custom Timeline
Connect your infrastructure for a personalized timeline estimate based on your actual readiness.
Next Steps
Frequently Asked Questions
What is the fastest way to get FedRAMP authorization?
What causes delays in FedRAMP authorization?
Can automation really reduce FedRAMP timeline?
How long does each phase of FedRAMP take?
Tags:
Related Articles
FedRAMP Authorization Guide (Pillar): From Readiness to ATO + Staying Authorized
A practical, end-to-end guide to FedRAMP authorization for cloud service providers—what to prepare, what goes into the package, what reviewers expect, and how to stay authorized after ATO.
FedRAMP FAQs & Myths: Straight Answers for CSPs
The most common FedRAMP questions (and myths) answered plainly—scope, paths, timelines, SSP/SAR/POA&M, 3PAOs, ConMon, and what reviewers actually care about.
FedRAMP Continuous Monitoring After ATO: Monthly, Quarterly, and Annual Checklist
You got the ATO—now what? This practical guide breaks down FedRAMP continuous monitoring (ConMon) after authorization: what to submit monthly, how to run the recurring cycle, and how to stay audit-ready without living in spreadsheets.
Ready to accelerate your FedRAMP journey?
Automate compliance and get FedRAMP-ready in weeks, not months
Start Free Trial →